The following section provides an overview of the major tasks required to implement the Regional Plan, including the development of deliverables outlined in this document.
DELIVERABLE | TASKS |
P4G Strategic Business Plan and Budget | • Develop biennial P4G Strategic Business Plan (PAC)
• Develop annual P4G Budget (PAC) • Review and approve biennial P4G Strategic Business Plan (ROC, P4GPC, Councils) • Review and approve annual P4G Budget (ROC, P4GPC, Councils) |
Reporting | • Provide annual reports to municipal Councils, including the Budget and Strategic Business Plan (ROC) |
P4G Regional Plan Review | • Coordinate review of Regional Plan approximately every 5–8 years (PAC, ROC, P4GPC, Municipalities)
• Develop required amendments to the Regional Plan (PAC, ROC, P4GPC, Municipalities) • Submit required amendments as per amendment process and receive approval (ROC, P4GPC, Municipalities) |
DELIVERABLE | TASKS |
P4G District Planning Agreement | • Develop and review P4G District Planning Agreement (PAC)
• Approve Agreement and submit to Councils for approval (ROC) • Submit approved Agreement to Minister for approval and Order (ROC) • Create P4G Planning Commission under the provisions of the Agreement (Councils) |
P4G Regional Plan | • Conduct a municipal review of the Regional Plan (Municipalities)
• Reconcile requested changes by Councils, if necessary (ROC) • Submit the Plan and receive approval from municipal Councils (Councils) • Submit the Plan to the Minister for approval (P4G) |
P4G Zoning Bylaw | • Development of P4G Zoning Bylaw (P4G)
• Review of P4G Zoning Bylaw (ROC) • Approval of P4G Zoning Bylaw (RM Council) |
Concept Plans | • Review and update draft Concept Plans (Municipalities, PAC, ROC, P4GPC)
• Develop schedule for municipality-led Concept Plans (PAC, ROC) • Coordinate ongoing efforts to develop Concept Plans (Municipalities, ROC) |
Inventory of Culverts and Drainage Infrastructure | • Coordinate inventory with regulators to compile required data on culverts and drainage infrastructure (PAC, ROC)
• Receive final inventory and distribute as required to support drainage infrastructure planning (ROC) |
Green Network Refinement Study | • Coordinate data requirements for the Refinement Study: digital elevation, survey of drainage infrastructure, etc. (PAC, ROC, municipalities)
• Coordinate Refinement Study to compile required data, conduct analyses, and provide recommendations for Green Network refinement (PAC, ROC) • Receive final report and distribute as required (ROC) • Develop required amendments to the Regional Plan (PAC, ROC) • Submit required amendments as per amendment process and receive approval (ROC) |
DELIVERABLE | TASKS |
Regional Alignment Statements | • Develop and submit Regional Alignment Statements (municipalities) |
Concept Plans | • Continue efforts to develop Concept Plans (Municipalities, PAC, ROC, P4GPC) |
Regional Commercial and Industrial Market Study | • Coordinate development of the Regional Commercial and Industrial Market Study (PAC, ROC)
• Receive final report and distribute as required (PAC, ROC) • Develop required amendments to the Regional Plan (PAC, ROC) • Submit required amendments as per amendment process and receive approval (ROC) |
Regional Potable Water Servicing Study | • Coordinate study to provide detailed options (if required) for regional delivery of potable water (PAC, ROC, Municipalities) |
Regional Potable Water Servicing Plan | • Develop Regional Potable Water Servicing Plan (if required) and submit to Councils for approval (PAC, ROC, P4GPC, Municipalities) |
Regional Wastewater Servicing Study | • Coordinate study to provide detailed options for regional wastewater facilities and infrastructure as a foundation for the Regional Wastewater Servicing Plan. (PAC, ROC, Municipalities) |
DELIVERABLE | TASKS |
Concept Plans | • Continue efforts to develop Concept Plans (Municipalities, PAC, ROC, P4GPC) |
Regional Wastewater Servicing Plan | • Develop Regional Wastewater Servicing Plan and submit to Councils for approval (PAC, ROC, P4GPC, Municipalities)
• Coordinate required regional wastewater infrastructure investment (PAC, ROC) |
Regional Transportation Demand Model + Plan | • Provide updates to the Saskatoon Regional Transportation Demand Model to permit use by P4G (PAC, ROC, Municipalities) |
DELIVERABLE | TASKS |
Regional Wetlands Inventory | • Coordinate study to develop Regional Wetlands Inventory (PAC, ROC)
• Receive final report and distribute as required (PAC, ROC, Municipalities) |
Regional Natural and Heritage Resources Inventory | • Coordinate study to develop Regional Natural and Heritage Resources Inventory (PAC, ROC, Municipalities)
• Receive final report and distribute as required (ROC) |
Regional Wastewater Servicing Study | • Coordinate feasibility study of options for second regional wastewater treatment plant (PAC, ROC, Municipalities) |
Regional Transportation Demand Model + Plan | • Develop Regional Transportation Plan and submit to Councils for approval (PAC, ROC, P4GPC, Councils)
• Maintain Saskatoon Regional Transportation Demand Model (PAC, Municipalities) |